How Long Do Pre-development and Obtaining a Building Permit Take?

How Long Do Pre-development and Obtaining a Building Permit Take?

05.02.2026

WZ, MPZP, ZPI, ZRiD, DŚU, the EIA report, PnB – short abbreviations do not mean quick decisions. See which stages most often prolong pre-development and what really affects the moment of “breaking ground”.

Introduction

Preparing land for a development in Poland is neither an easy nor a quick task. In practice, real estate pre-development usually takes 1.5 to 2.5 years, but there are developments in Poland whose preparation took more than 10 years. Of course, the time needed to prepare a given plot depends on the size of the development, its location and its level of complexity. Where, though, does such a long time come from?

Stage zero – preliminary property analysis (before acquisition).

This stage usually takes far too little time. A basic analysis of an investment plot reduced to a capacity study, covering a cursory check of the local spatial development plan or Zoning Decision, is usually not enough. From practice, we recommend carrying out a comprehensive analysis – we call it the 360o Property Analysis – in order to identify the key risks when buying a plot: planning, legal, environmental, social or political.

Stage one – environmental.

This is where the difficulties begin – if the development requires an environmental decision, it is necessary to prepare a project information sheet (KIP) and obtain a number of opinions (the Regional Directorate for Environmental Protection, the State Water Holding “Polish Waters”, the sanitary inspectorate). The duration is from 6 to 12 months, to which one must add the time needed to prepare an advanced architectural concept that will make it possible to supplement the KIP. Sometimes, because of environmental requirements or the low quality of the project information sheet, multiple supplements are required, each of which can prolong the process by many weeks. The environmental decision can be appealed by parties to the proceedings (everyone who owns property in the area of impact and the consulted authorities).

And then the impact report

The quality of the study, but also environmental conditions, may additionally lead the authority to issue a ruling requiring an environmental impact assessment report (EIA report). That is an additional 12 months or more – depending on the exact content of the ruling. In the worst case, however, work on the report may only begin after six months – when its preparation requires a specific season (breeding period, plant growing season) and frequency of surveys. Ultimately, an environmental decision prepared at an early stage of the project often has to be amended later, together with modifications to the architectural concept.

Stage two – planning decisions

A Zoning Decision should be issued (for larger developments) within 90 days. Since the prospect of restricting the issuing of Zoning Decisions appeared on the horizon, the way urban planning analysis is carried out has changed, and sanctions for delays by offices ceased to apply, this deadline has become purely theoretical. The same is true of the deadline for issuing location resolutions under the “Lex Developer” Act. Adopting a local spatial development plan takes a minimum of 6 months, and in practice rather 9 to 15 months. A somewhat shorter time should be assumed for the Integrated Investment Plan (ZPI), introduced as part of the spatial planning reform in Poland. However, the authorities’ limited experience in applying the regulations in this area must be taken into account. Here we also often see resolutions being annulled by the supervisory authority (the voivodeship office).

Changes to planning decisions

Having a planning decision does not always make the situation easier – if it needs corrections, the procedure for changing it is difficult at the very least. Changing a Zoning Decision requires the consent of all parties, so in practice the only option is to apply for a new decision. Changing a plan takes a time similar to adopting it, and no one has yet carried out a change to a location resolution or an Integrated Investment Plan. A faster “simplified” procedure has admittedly been provided for the local spatial development plan, but reading the regulations leaves no doubt – it is easier to meet a Yeti than a situation in which it would be permissible. In practice, where a plan amendment is difficult to carry through, we have in a few cases turned to the ZPI – provided, of course, that the municipality is ready for it and is not overwhelmed by the effects of the 2025 changes in spatial planning.

If problems arise, the route of interpreting the act remains – but it is possible only for some doubts (not for changes!).

Stage three – the building permit

The statutory 65 days does not cover the period of formal review, supplementing applications at the request of the authorities and periods of suspension of the proceedings, so in practice this stage takes a minimum of 4 months. Many related decisions may also be needed. Possible permits for rebuilding technical infrastructure, demolition decisions or related proceedings (e.g. concerning renovations or works on neighbouring plots) can extend this time even further. Where a road development is delivered on the basis of a ZRiD decision (permit for the delivery of a road project), we must expect an even longer time. Preparing the documentation and processing it is also far more complicated. A ZRiD is an integrated decision covering the building, subdivision and expropriation decisions, and in practice this gives rise to many problems.

Conclusions

Pre-development is by nature a complicated and lengthy process. It is therefore worth turning to proven investment advisers who will optimise its duration. Some preparations can be run in parallel, some can be carried out in advance, and above all it is worth doing everything to avoid repeating or changing decisions already obtained and stages already closed.

FAQ

In a typical scenario, preparing a development takes from 1.5 to 2.5 years, assuming no major formal or environmental complications. During this time the investor goes through the preliminary analysis stage, the environmental procedure (if required), obtaining planning and administrative decisions, and the building permit.