Case studies: pre-development and advisory projects

A complex of multi-family buildings with services and an accompanying road layout and public square.

We began working together when the project had reached a standstill and the investor saw no prospect of completing a project that had fixed deadlines written into the agreement with the fund financing the development.

 

  • We prepared and signed a framework agreement with the local authority
  • We carried out the necessary land divisions
  • We agreed the necessary changes to the draft local spatial development plan
  • We acquired, through an exchange, the properties missing for the development to proceed
  • We obtained legal titles to dispose of the properties for building purposes and the easements necessary to deliver the project
  • We coordinated the work of architects and engineers to optimise the duration of the design work
  • We negotiated with the architectural and building administration and the heritage conservator to obtain the building permit efficiently
Read more

A development in the centre of a large city with difficult neighbours

After signing the preliminary agreement, the investor commissioned us to coordinate the work leading to a building permit in dense city-centre development, with buildings entered in the register and records of monuments on the property and in its immediate vicinity.

 

  • We held arrangements with one of the infrastructure operators to relocate elements of the network to the adjoining plot of a neighbouring residents’ association
  • We agreed with the residents’ association, and obtained its consent, to locate a transmission network on its land and to bricking up windows, reinforcing the roof and other works necessary because the association’s buildings stand on the boundary with the investor’s property
  • We agreed with a public institution neighbouring the property a change to the scope of its active permit for conservation works on its building, and agreed those changes with the voivodeship heritage conservator
  • We agreed the reconstruction of infrastructure, including the tram traction network, in the area adjoining the property in order to obtain a driveway from the public road
  • We negotiated with the voivodeship heritage conservator the scope of changes to a building entered in the heritage records

 

A complex of multi-family buildings on a former industrial site in the city centre

We began working together in a situation where the development had been blocked by social protests, despite a local spatial development plan being in force for the area.

 

  • We analysed the possibilities of changing the scope of the development without losing usable floor area on the basis of the “Lex Developer” Act
  • We agreed a change to the agreement for the preparation of a ZRiD decision (permit for the delivery of a road project) to one that did not interfere with the trees and was sufficient to serve the new development
  • Together with the design studio we prepared a concept for the application for a location resolution, and held negotiations with the heritage conservator, the city architect and the road manager
  • We obtained the necessary opinions and, ultimately, a resolution consenting to the location of the residential development

A commercial building on the edge of a city next to a road being rebuilt

We began work when the investor was under time pressure arising from protracted arrangements with the public administration, in the context of the deadline for obtaining a building permit set out in the agreement with the property’s eventual buyer.

 

  • We held arrangements with the owner of the water and sewage network, the road manager and the entity responsible for road projects;
  • We agreed traffic access with the road manager and environmental protection authorities, because of a conflict with existing trees,
  • We resolved additional minor problems, which made it possible to obtain the building permit before the contractual deadline expired.

A development under the “Lex Developer” Act

We were asked for help at the moment when the resolution had received a preliminary negative opinion from a committee of the municipal council.

  • We identified all the stakeholders who were critical of the development;
  • We agreed with the office an adjustment of the concept to the officials’ expectations;
  • We determined the conditions for serving the development and obtained a positive opinion from the road manager;
  • We negotiated the scope of the agreement on the associated development;
  • We monitored the process at every stage of opinions and approvals until the municipal council adopted a positive resolution.