That is why good pre-development begins before the plot is acquired – solid due diligence, analysis of legal and planning conditions and access to infrastructure, capacity analysis, but also an assessment of the competition and the attitude of the public administration, are crucial before taking the decision to invest.
A Multi-Family Housing Estate with a Road Layout and Public Square – Case Study
A complex of multi-family buildings with services and an accompanying road layout and public square.
We began working together when the project had reached a standstill and the investor saw no prospect of completing a project that had fixed deadlines written into the agreement with the fund financing the development.
- We prepared and signed a framework agreement with the local authority
- We carried out the necessary land divisions
- We agreed the necessary changes to the draft local spatial development plan
- We acquired, through an exchange, the properties missing for the development to proceed
- We obtained legal titles to dispose of the properties for building purposes and the easements necessary to deliver the project
- We coordinated the work of architects and engineers to optimise the duration of the design work
- We negotiated with the architectural and building administration and the heritage conservator to obtain the building permit efficiently
FAQ
Pre-development usually takes from about 1.5 to 2.5 years – depending on the size of the development, its location and its level of complexity. This time is made up of, among other things, the environmental stage (an environmental decision usually takes 6–12 months, and a possible environmental impact assessment report can add 12 months or more), the planning stage (adopting a local plan in practice takes 9–15 months, and a Zoning Decision often takes much longer than the statutory 90 days) and preparing and agreeing the documentation for the building permit.
Pre-development time is most often prolonged by: repeated supplements to documentation at the authorities’ request (each can add many weeks), appeals against decisions by parties to the proceedings, the need to prepare an environmental impact assessment report (surveys are sometimes possible only in a particular season), the authorities’ limited experience in applying new regulations, annulments of resolutions by the supervisory authority, protests from neighbours and the local community, and problems with access to a public road and utilities.
At the pre-development stage it is possible to identify, among other things, planning uncertainty or the need to change the interpretation of regulations, problems with road access and traffic arrangements, collisions and technical constraints (ground, infrastructure, buildings on neighbouring plots), environmental and legal risks, and procedural delays together with the cost of frozen capital. The biggest mistake is “going to design” before the critical risks have been closed – you then pay for the design, for the time and for the corrections.