How long does an Integrated Investment Plan take and what does it cost? Procedure stages and budget

How long does an Integrated Investment Plan take and what does it cost? Procedure stages and budget

27.10.2026

The Integrated Investment Plan (ZPI) allows the designated use of land to be changed for a specific project, but it is not a quick route. An investor who is buying land or planning financing needs to know how many months the procedure will take and what costs will arise before applying for a building permit. Below we set out both.

ZPI procedure step by step

The procedure was introduced by the 2023 reform of the Spatial Planning and Development Act. In simplified terms it looks like this:

  • Initial analysis. Checking the legal status of the plot, the provisions of the municipal general plan, access to a public road, utilities and environmental constraints.
  • Concept and application. Preparing the draft plan, the urban and architectural concept (if required), the ecophysiographic study and the application to the commune head, mayor or city president.
  • Council decision to proceed. The council may accept the application or reject it. The municipality is not obliged to agree to start work on the ZPI.
  • Revising the draft plan. This covers the strategic environmental impact assessment, opinions and approvals from public bodies and public consultation.
  • Urban planning agreement. Negotiating and concluding the agreement in which the investor commits to the supplementary investment.
  • Adoption and entry into force. The municipal council adopts the plan, the voivode (provincial governor) has 30 days to check its legality, and the plan comes into force two weeks after publication in the official journal of the voivodeship.

How long an Integrated Investment Plan takes

The Act does not set a single deadline for the whole procedure, and municipalities are only now building up practice, so the figures below are planning estimates, not a guarantee:

  • preliminary analysis and concept: 1 to 3 months,
  • consideration of the application by the head of the municipality and the council: 1 to 3 months, depending on the calendar of council sessions,
  • agreeing the final draft plan, statutory approvals and consultation: 6 to 12 months,
  • resolution, publication and entry into force: about 3 months.

A realistic horizon is therefore most often 12 to 18 months. The time is extended by residents’ protests, the absence of a general plan, comments from approving bodies and disputes over the scope of the urban planning agreement. It can be shortened mainly through preparation: a complete analysis and concept before the application is filed reduce the number of revisions at later stages. An early conversation with the authority and councillors, before the application formally reaches a session, also helps, because it reveals what the municipality expects from the supplementary investment.

ZPI cost: what makes up the budget

The cost of an Integrated Investment Plan consists of several groups of expenditure:

  • specialist studies: a green inventory and other nature surveys, ecophysiography, environmental forecast, traffic analyses,
  • draft plan and concept: the work of an urban planner and an architect,
  • costs on the municipality’s side: some municipalities expect the investor to prepare the environmental impact assessment and to revise the plan following comments and opinions,
  • supplementary investment: a road, utility networks, a nursery school or green space under the urban planning agreement, usually the largest item,
  • planning levy: up to 30% of the increase in property value if the property is sold within 5 years of the plan coming into force,
  • compensation for planning blight: the municipality may pass on to the investor the duty to make good losses connected with the plan coming into force. In practice this may arise where the plan covers private land not owned by the investor.

The amounts depend on the scale of the project and the municipality, so the budget should be calculated in a financial analysis before the land is bought. We explain how to negotiate the largest item, the supplementary investment, in our guide Urban planning agreement in a ZPI. If you would like someone to run the whole process for you and keep to the timetable, see how we handle the Integrated Investment Plan from analysis to resolution.

Frequently asked questions: how long a ZPI takes and what it costs

Usually yes, because the investor drives the procedure by supplying the studies and the concept instead of waiting for the municipality’s planning schedule.